Onestopbankingexams

Dear users we are very happy to announce that from now on we would be moving to a better organised portal.


New Users Please register here


http://www.bankexam.smffy.com

U are hereby requested to register at the above given location and post your queries there.....

Existing users please register there...

Join the forum, it's quick and easy

Onestopbankingexams

Dear users we are very happy to announce that from now on we would be moving to a better organised portal.


New Users Please register here


http://www.bankexam.smffy.com

U are hereby requested to register at the above given location and post your queries there.....

Existing users please register there...

Onestopbankingexams

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Onestopbankingexams

This is a Forum for all your Bank exam needs - Clerical , Probationary Officer PO , Specialist Officer SO , Assistant Manager AM , Management Trainee MT.


3 posters

    Time and Work & Wages

    nandu
    nandu

    Forum Member

    Forum Member


    Posts : 8
    Join date : 2011-05-03
    Age : 40
    Location : Chennai

    Time and Work & Wages Empty Time and Work & Wages

    Post  nandu Tue May 17, 2011 2:45 pm

    8 women and 3 boys can complete piece of a work in 15 days.
    In how many days will 12 women and 2 boys complete the same piece of work?

    Options:

    1.12 2. 8 3. 6 4. cannot be determined. 5. none
    Abhishek
    Abhishek

    Forum Admin
     Forum Admin


    Posts : 547
    Join date : 2011-04-08
    Age : 36
    Location : Kolkata

    Time and Work & Wages Empty Re: Time and Work & Wages

    Post  Abhishek Tue May 17, 2011 5:55 pm

    nandu wrote:8 women and 3 boys can complete piece of a work in 15 days.
    In how many days will 12 women and 2 boys complete the same piece of work?

    Options:

    1.12 2. 8 3. 6 4. cannot be determined. 5. none


    There is a formula for solving such problems -

    If a men and b women can do a piece of work in n days then c men and d women can do the same piece of work in :


    Time and Work & Wages TimeworkHere

    n = 15

    a = 8

    b = 3

    c = 12

    d = 2


    Hence applying the formula we get :

    15* 8* 3 / (12*3 + 8*2 )

    =>360 / 52

    =>60/7 days

    8.xxxx

    Make this formula as a thumbrule for solving such problems...

    Similar formulas exists for a men or b women type problems . I will request U to pour in such questions here in this thread.....

    avatar
    narendaz

    Forum Member

    Forum Member


    Posts : 1
    Join date : 2011-10-28

    Time and Work & Wages Empty सर =>360 / 52 =>60/7 days कैसे हो गये है

    Post  narendaz Fri Oct 28, 2011 2:33 pm

    Abhishek wrote:
    nandu wrote:8 women and 3 boys can complete piece of a work in 15 days.
    In how many days will 12 women and 2 boys complete the same piece of work?

    Options:

    1.12 2. 8 3. 6 4. cannot be determined. 5. none


    There is a formula for solving such problems -

    If a men and b women can do a piece of work in n days then c men and d women can do the same piece of work in :


    Time and Work & Wages TimeworkHere

    n = 15

    a = 8

    b = 3

    c = 12

    d = 2


    Hence applying the formula we get :

    15* 8* 3 / (12*3 + 8*2 )

    =>360 / 52

    =>60/7 days

    8.xxxx

    Make this formula as a thumbrule for solving such problems...

    Similar formulas exists for a men or b women type problems . I will request U to pour in such questions here in this thread.....


    Sponsored content


    Time and Work & Wages Empty Re: Time and Work & Wages

    Post  Sponsored content

      Similar topics

      -

      Current date/time is Fri Mar 29, 2024 1:54 am